How to price a flooring tender

Read the tender pack, check the bill against your own takeoff, build rates that hold up on site, and qualify what the documents leave open.

A tender isn't a bigger domestic quote. You're pricing someone else's drawings, specification and often quantities, to a deadline, and if you win on a rate that doesn't cover the real job, you're held to it. Here's how an experienced contract flooring estimator prices one. For jobs you've measured yourself, see how to quote a flooring job.

1. What's in a flooring tender pack

Before measuring, list what you've been sent and what's missing. A typical flooring package includes:

Check drawing revisions against the drawing register. Pricing a superseded drawing is an easy, expensive mistake.

2. Read the specification before you measure

The specification says what you're pricing; the drawings only show where. Older-style NBS specifications put rubber, plastics, cork, lino and carpet tiling and sheeting under CAWS M50, and cement-based screeds under M10; newer ones use Uniclass codes. For each flooring clause, note:

3. Measure from the drawings, and check the scale

Take off the drawings yourself even when there's a bill, room by room, with references.

On a large pack, flooring estimating software can take the first pass, but these checks still apply.

4. Check the bill of quantities against your takeoff

A bill is somebody else's measure. Compare it with yours line by line.

Know the measurement rules. The preambles say which were used, and many UK bills follow RICS NRM2 (detailed measurement for building works). NRM2 measures floor finishes as the net area in contact with the base, doesn't deduct voids of 1 m² or less, and includes cutting and waste in the item. The bill won't allow for your waste; your rate must.

When the figures differ:

Never absorb a gap silently. Some contracts correct wrong bill quantities; on a lump sum priced from drawings and specification, they're your risk. The subcontract and preambles say which.

5. Build your rates

Build every rate from real costs, not a remembered number:

Get supplier prices for this project, and note how long they're held.

6. Worked example: building one bill rate

One bill item priced from the ground up. All figures are illustrative, not market rates. Coverage varies by product, so use your own prices and the manufacturer's data sheets.

Example only: supply and lay 2 mm safety sheet vinyl to corridors, 186 m² as billed
CostWorking (illustrative)Amount
Sheet vinylCutting plan: 107 m of 2 m wide roll = 214 m² × £19.50£4,173.00
Adhesive186 m² ÷ 50 m² per tub = 3.72, so 4 tubs × £62.00£248.00
Smoothing and primer3 mm: 186 m² × 3 × 1.5 kg = 837 kg ÷ 25 kg = 33.48, so 34 bags × £16.00, plus primer £96.00£640.00
Weld rod2 reels × £28.00£56.00
Laying and welding186 m² × £11.00£2,046.00
Preparation labour186 m² × £4.00£744.00
SundriesProtection, waste removal and consumables£350.00
Net cost £8,257.00
Overheads and profit15% of £8,257.00£1,238.55
Price for the item £9,495.55
Bill rate£9,495.55 ÷ 186 m², rounded£51.05/m²

The bill says 186 m², but the cutting plan buys 214 m². Price only 186 m² of vinyl and the other 28 m² (£546.00 here) comes out of your margin. And the 3 mm smoothing depth is an assumption, so qualify it.

7. Preliminaries, programme and phasing

Preliminaries are the cost of being on the job: supervision, travel and mobilisation for each visit, parking, access equipment, storage, RAMS and inductions, samples and O&M information. Price them as a lump sum or within your rates, and say which. Under NRM2, you're assumed to have allowed for defined provisional sums in your programming, planning and preliminaries.

Then count your visits on the programme: four phased handovers are four mobilisations. Check the window allows for a ready base, a weathertight building at the conditions the specification requires, and material lead times. Price return visits, or state how many are included.

8. Qualifications, exclusions and clarifications

State exactly what your price is based on:

Be specific. Main contractors level competing tenders, and vague lines like "subject to survey" tend to be priced against you.

9. Retentions, payment terms and CIS

Price isn't the only number that matters. Check the subcontract for:

This is general information, not legal or tax advice.

10. Submit, then follow up

11. Common tender pricing mistakes

12. The estimator's checklist

How BillyBot handles a tender pack

BillyBot is an AI operator that runs the office side of a flooring business, from first enquiry to final invoice, tenders included. When a tender pack is emailed to your connected Gmail or Outlook inbox, Billy gets to work on it.

  • Takes off the drawings and the bill, so you start from a measured scope instead of a blank spreadsheet.
  • Picks out the flooring scope from the specification, so you can see what's in your package and what isn't.
  • Prices on your own rates, never an average someone else chose.
  • Flags what needs your eye instead of guessing, so you know exactly what to check before the price goes out.

The quote is only created when you confirm it, as a PDF or in Xero, Sage or QuickBooks. More on the flooring estimating software page.

Pricing a flooring tender: FAQ

Read the pack and the specification first. Take off the drawings after checking the scale, compare your figures with the bill and query real differences. Build rates from what you'll actually buy, labour, preparation, access, protection and waste, add preliminaries, then write your qualifications and check the payment terms.

A bill of quantities gives a measured quantity for each item, so you price every line and the total is your tender. A schedule of rates has no firm quantities: you price a rate per unit and the work is measured as it's instructed, which is common on maintenance and term contracts.

No. Under RICS NRM2, floor finishes are measured as the net area in contact with the base, with cutting and waste included in the item. Cost the quantity you'll actually buy, including roll and pack rounding, and spread that cost over the billed area.

Price the bill for small differences from rounding or small voids. For a real gap, such as a missing room, raise a tender query before the deadline or qualify it. Never absorb it silently, and check whether the contract corrects bill errors or leaves the risk with you.

Measure a written dimension on the drawing and compare it with the scale bar and the ratio in the title block. A 1:100 drawing on A1 becomes 1:200 when issued at A3, so trust the scale bar or the written figures over the ratio.

It can do much of the reading and measuring, but an estimator should still check the result. BillyBot reads tender packs emailed to your connected inbox, takes off the drawings, prices on your own rates and flags anything it couldn't read or measure, for you to review and confirm.